The East Hub Development started in 2016

Source: eni.com

East Hub Development

The East Hub Development Project is an area located in Block 15/06 offshore Angola with nine sub-sea wells – five producers and four water injectors – at a depth of between 450m and 550m. The hydrocarbons produced are transported via a system of pipes to the FPSO Armada Olombendo, where they are treated and stored before being exported. Production in the Cabaça South East field, 350km north-west of Luanda and 130km west of Soyo, began in February 2017, five months ahead of schedule. For this reason the East Hub Development is one of seven record-breaking projects from Eni, all of which are remarkable for their rapid approval rates and times to start-up.

Learn more Source: eni.com

Project Key-Facts

  • Project name East Hub
  • Country Angola
  • Operator Yes
  • Start-up Achieved
  • Equity peak in 4 YP (kboed) 20
Source: 2016-2019 Strategy Presentation

Plants

  • Armada Olombendo

    The FPSO Armada Olombendo is a floating production, storage and offloading unit that operates offshore Angola as part of the East Hub Development Project. It can produce up to 80,000 barrels of oil a day and compress up to 3.4million m3 of gas. With nine sub-sea wells – five producers and four water injectors – at a depth of 450m, the FPSO enabled production to begin at the Cabaça South East field, 350km north-west of Luanda and 130km west of Soyo.

ENI's great transformation - Fit for complexity

Eni has changed a lot during the last three years in order to face the challenges of the market and to better address the three major shocks that have affected the energy sector: the collapse of gas consumption in Europe; the decline of oil demand in Europe and refining margins ...

eniday

From Enivideochannel

Visit the official channel YouTube

The story of the FPSO construction - East Hub Project | Eni Video Channel

On 14th October 2016, we celebrated, along with our Angolan partner Sonangol, the launch of FPSO Armada Olembendo in Singapore. Find out more on https://www.eni.com/en_IT/operations/stories-people/fpso-armada-olombendo.page?lnkfrm=serp Subscribe on Eni Video Channel https://www.youtube.com/channel/UC4T5-TgmOJWXgeOLGwj-Ekw ----- Want more from Eni? Facebook: https://www.facebook.com/EniItalia/?fref=ts Twitter: https://twitter.com/eni https://twitter.com/Eniday Instagram: https://www.instagram.com/eni/ Flickr: https://www.flickr.com/photos/enidigital/albums Google+: https://plus.google.com/u/2/106162487688494239281/posts

From Enivideochannel

Visit the official channel YouTube

Aboard of Armada Olombendo - East Hub Development Project | Eni Video Channel

Eni's Ceo, Claudio Descalzi, on board of Armada Olombendo to celebrate the departure of first oil from the East Hub Development Project. Find out more on https://www.eni.com/en_IT/operations/stories-people/fpso-armada-olombendo.page?lnkfrm=serp Subscribe on Eni Video Channel https://www.youtube.com/channel/UC4T5-TgmOJWXgeOLGwj-Ekw ----- Want more from Eni? Facebook: https://www.facebook.com/EniItalia/?fref=ts Twitter: https://twitter.com/eni https://twitter.com/Eniday Instagram: https://www.instagram.com/eni/ Flickr: https://www.flickr.com/photos/enidigital/albums Google+: https://plus.google.com/u/2/106162487688494239281/posts

The East Hub Development Project in Angola, a journey in pursuit of excellence

News The East Hub Development Project in Angola, a journey in pursuit of excellence Block 15/06 is one of Eni's most important assets: a project crowned with success. East Hub is one of the site's two [...] Angola as part of the East Hub Development Project. The FPSO ...

9 November 2016 eni.com Section: operations

2016 portfolio development

production re-start of the Kashagan field (Eni's interest 16.81%) with the fully replacement of the damaged pipelines. Production capacity of 370 kbbl/d is expected by the end of 2017 start-up of M'Pungi [...] Hub Development project in the offshore Block 15/06 (Eni operator with ...

9 August 2017 eni.com Section: enipedia

The assets and operations of development of Eni's oilfields

production re-start of the Kashagan field (Eni's interest 16.81%) with the fully replacement of the damaged pipelines. Production capacity of 370 kbbl/d is expected by the end of 2017; start-up of M'Pungi [...] Hub Development project in the offshore Block 15/06 (Eni operator with ...

4 May 2017 eni.com Section: operations

Exploration model

between discovery and start-up in Nooros, Egypt, and gas production has reached 20m cubic metres per day. In record time, less than three years after the FID, OCTP in Ghana - a project that integrates the [...] analyses for development are made during exploration. The information collected enables us to improve ...

31 August 2017 eni.com Section: operations

Eni’s operations: mission, challenges and exploratory successes

accidents UPSTREAM FPSO N' Goma - West Hub Project Armada Olombendo - East Hub Development Project Load out - Jangkrik Complex Project Goliat, the Giant - IV The start of the production A record breaking field [...] Mediterranean Sea; on Nooros, offshore in the Nile Delta; and in the Republic of Congo on the Nené ...

10 August 2017 eni.com Section: operations

In pursuit of excellence

of Angola, in Block 15/06 , as part of the East Hub Development Project. The complexity and difficulty of creating plants such as the East Hub Development Project stem from the fact that the skills and technologies [...] In pursuit of excellence East Hub and West Hub Projects in Angola, in ...

6 November 2017 eni.com Section: operations

Eni’s activities in Angola

with a 36.84% interest) at the end of 2014 with the West Hub Development Project that represents the first Eni-operated producing project in the Country. The development program plans to hook up the Block's [...] injection wells in line with the zero flaring policy. In February 2017, production start ...

12 May 2016 eni.com Section: enipedia

First half 2017 Results

Cabaça South East field began after just three years - five months ahead of schedule. The second project involved both oil and gas development: production started after just over two years, giving local [...] a major new area of exploration for Eni, with two wells drilled in the Amoco field. Thanks to ...

2 August 2017 eni.com Section: operations

First half 2017 Results

Cabaça South East field began after just three years - five months ahead of schedule. The second project involved both oil and gas development: production started after just over two years, giving local [...] a major new area of exploration for Eni, with two wells drilled in the Amoco field. Thanks to ...

2 August 2017 eni.com Section: operations

In pursuit of excellence

operate offshore of Angola as part of the East Hub Development Project. The complexity and difficulty of creating plants such as the East Hub Development Project stem from the fact that the skills and technologies [...] increase total production from the prolific 15/06 field to 150,000 barrels per day ...

25 May 2017 eni.com Section: operations