Eni’s results in 2016 in the company’s annual profile.
In brief, the company’s achievements during the year.
E&P projects: progressed construction activities at our development projects expected to come on stream in 2017 (Jangkrik - Indonesia, OCTP oil - Ghana and Zohr - Egypt). In Februray 2017, started-up the East Hub project in Angola, five months earlier than scheduled. These projects, together with the ramp-up of 2016 new production from Kashagan and Goliat, will strongly contribute to the cash generation in 2017 and following years. In three years, projects break-even reduced leveraging on the exploration strategy, driven by the target of cost optimization in develop resources in production, effective development model and operating costs reduction.
Goliat: start-up of Goliat field (Eni operator 65%) in the Barents Sea. Reached the production target of 100 kboe/d (65 kboe/d net to Eni).
Kashagan: restarted Kashagan field with the completion of the replacement of the damaged pipelines. Production capacity is expected to reach 370 kbbl/d in 2017.
Nooros: reached a production plateau of 85.5 kboe/d net to Eni from the Nooros field located in Egypt. This record-setting production level was reached in just 13 months after the discovery in July 2015 and ahead of schedule. With the drilling of additional development wells, the field is expected to reach a maximum production capacity of about 160 kboe/d in 2017. Nooros is an important achievement by Eni’s “near-field” exploration strategy, aimed at unlocking the presence of additional exploration potential located in proximity to existing infrastructures.
Zohr: sanctioned by the Egyptian Authorities the development plan of the Zohr discovery, where production start-up is expected by the end of 2017. Completed the drilling of wells and successfully performed the production test, which confirmed the mineral potential of the discovery.
Mozambique: authorities approved the development of the first development phase of Coral, targeting production of 5 tcf of gas. The Area 4 partners (Eni East Africa, joint operation between Eni and CNPC, Galp, Kogas and ENH) and BP signed a binding agreement for the sale, over a 20-year period, of approximately 3.3 million tons of LNG per annum (corresponding to about 5 bcm), which will be produced at the Coral South Floating facility.In March 2017, ExxonMobil and Eni signed a sale and purchase agreement to acquire a 25% indirect interest in the Area 4 block, offshore Mozambique. The agreed terms include a cash price of approximately $2.8 billion. The completion of the deal is subject to satisfaction of certain conditions precedent, including clearance from Mozambican and other regulatory authorities.
Forgotten Password? Retrieve
it
(only for Associazioni Consumatori)
Inserisci l’indirizzo email con il quale ti sei iscritto a eni.com. Riceverai all’indirizzo indicato la nuova password, che ti consigliamo di aggiornare dopo il primo accesso.
Operation successfully completed. Please check your mail address.